A sample of the Friday report
Friday.
Helen Ward, project lead, to the owners. One page. The same page every week.
This week
- Plaster in the stair hall is a week late. The keys failed on the north wall. 12 June moves to 19 June.
- The oak on the second floor is down. The 1926 boards in the hall stay. The vinyl in the old kitchen is gone.
- The village had no further comment on the west eave. The hearing is closed.
Money
- Design fee $28,400, credited to the build in full.
- Plaster allowance $46,000–$62,000. The delay does not change it.
- Decision by Wednesday: the bath stone. The letter next Friday will record which one.
Next week
- Sister the joist at the maid’s stair. The original timber stays in the section.
- The shop cuts a casing mockup to the 1926 profile, for you to see on site Thursday.